Internal Work January 2025





Timber studwork

12 January 2025


Plasterboard upstairs

12 January 2025



Plaster skim

12 January 2025


Services in porch

23 January 2025



Topcoat render

25 January 2025


Basecoat on garage

4 February 2025



Scaffolding comes down

12 February 2025


Front elevation

12 February 2025



Heating turned on

1 March 2025


Strengthening under beams

17 March 2025


Light weight blocks replaced with high density ones under supporting beams

Plastering finished

27 March 2025


Staircase Delivered

6 April 2025



Stairs installed

17 April 2025


I Square Doorway up

19 April 2025



Door Installed

23 April 2025


Start on internal doors

2 May 2025



Subsoil gone and fence finished

22 May 2025


Kitchen Fitted

10 June 2025