Finishing Off June 2025




Some junk from Willow Bank

5th June 2025


Willow Bank goes on the market. The Agent is planning an Open Day
on 12 July. We get an early viewing and they make an offer which
we accept and cancel the viewing day

Waiting for the lift door

30 June 2025



Start doors on Batcave

5 July 2025


Door frame for the Batcave

27 July 2025



Pavers for patio delivered

5 August 2025


Wall for raised flower bed

9 August 2025



Start frame for Airing Cupboard

9 August 2025


Batcave doors finished

13 August 2025



Other door finished

13 August 2025


Airing Cupboard doors hung

13 August 2025



Stiltz start on lift

14 August 2025


Start wiring freezer

24 August 2025



Curtains hung in bedroom

28 August 2025


Line Freezer room walls

9 September 2025



Start Patio

10 September 2025


Finish Patio

20 September 2025



Level soil for lawn

29 September 2025


Collect composite cladding

1 October 2025



Start fixing cladding

2 October 2025


Soil in flowerbed

1 November  2025



Showerroom floor 

24 November 2025


Asphalt  to Seal store room

24 November 2025



Tile Shower room floor

3 December 2025