Second week working full time

4th (20 ton) load of stone for drive

25 April 2024


Tiping 4th 20 ton load of stone

Block and Beam floor started for drive

25 April 2024


First part of drive B&B floor

Beams being placed

26 April 2024


placing beams for drive

Video of placing Concrete Beams

26 April 2024


These beams weigh about 160 Kg (350 lb) each


Steel Beams for supporting floor

26 April 2024


steel beams

Video of placing Steel lintel

26 April 2024



Brick layers work on house

26 April 2024


view of house

Beams in place and more house walls

1 May 2024


beams in place

House reaches First Floor level

3 May 2024


First floor level

View of kitchen window

3 May 2024


Kitchen window